Litostroj Power is building new Turbine and Generator production facility in Ankara (Turkey), which is located 50 km southwest of Ankara in the Second Organized Industrial Zone, next to the motorway E90 from Ankara to Polatli.
Our Greenfield investment is being constructed on 32.000 sqm and will enable to support entire turbine and generator production process, from metal processing (cutting, annealing and hardening) to welding, machining and final assembly of our products. When fully operational, factory will employ between 150 – 200 employees.
All main construction work like concreating, roof & facade covering, main door installation, rainwater drainage system and overhead crane erection are finished. We are now moving into the main mechanical and electrical works which are planned to be finished until June 2018, followed by major machinery erection and installation activities. First production activities are planned to start before the end of this year.
See the video about construction of new production facility