Show menu

Project Maris South Canal successfully put into commercial operation

Ljubljana, 28. 12. 2017
In the last days of 2017, the site works on Maris South Canal project in Philippines came to a successful end. A team of Litostroj Power engineers and its partners concluded the wet testing of two 4,4 MW Pit Units which were put into commercial operation. 

Additional to the turbine equipment, Litostroj Power also supplied the generators and the Electrical balance of plant equipment in collaboration with its partners.  

The completion of the project represents the first Water to Wire project constructed by Litostroj Power in the in Southeast Asia. Thanks to aligned production and assembly processes and well-coordinated project management of all involved partners, all the works were completed ahead of the contractual schedule and within the budget.